PROJECT in a box - Project Report

Contents

Project
Project Summary Information
Temporary Office
Wing 1
User Activity
Risk Log Summary
Issue Log Summary
Quality Log Summary
Finance Log Summary
User Specified Spreadsheet Tables
User Specified MSP Plans

Project and Stage Status

Project Stage
Town hall extension Temporary Office Wing 1

On Track 

Completed 

Not Started 

Summary Information [top]

General
Project Name Town hall extension 
Report Date 2010-02-17 15:52:45
Updated Date 2009-09-09 13:58:30
Description  
Commentary  
Status
On Track 
Project_Manager Mike Nesbitt
Project_Sponsor Micky Rourke
Business_Area Estates
Customer Chief Execs office
Method_Template P22009 core
Value 4500000
Duration 70
Risk 4
Reward 7
Strategic_Alignment good

Project Roles [top]

Executive guy
Project Assurance paul
Project Manager malc
Senior Supplier Emma
Senior User nick

Stage Highlight Report [top]

General
Project Name Town hall extension 
Stage Name Temporary Office 

Highlight Report.xls

Document: 'Highlight Report' File: 'Highlight Report.xls' Version: 0.0.b Date: 2009-09-08 10:35:17 (data provider:excelgembox)

General
Project Name Town Hall Extension
Stage Name Temporary Office
Project Manager
Report Date 08/09/2009
Status Summary, (an overview of the status of the stage at this time)
Project and Stage Tolerance Status (how execution of the project and stage are performing against its tolerances e.g. Cost/time/scope actuals and forecast)
Requests for Change (Identifying any raised, approved/rejected and pending)
Key Issues and Risks (summary of actual or potential problems and risks)
Lessons Report (if appropriate a review of what went well, went badly and any recommendations for corporate or programme management consideration)
This Reporting Period
Work Packages
Ref no and name status and notes
Products
Ref no and name Status and notes
Corrective Actions undertaken
Next Reporting Period
Work Packages
Ref no and name status and notes
Products to be completed
Ref no and name Status and notes
Corrective Actions to be undertaken

Stage Status

Product Descriptions Approved Yes
Work Packages Defined Yes
Stage Plan Produced Yes
Stage Started Yes
Stage Completed Yes
Stage Deliverables Approved Yes

Stage Highlight Report [top]

General
Stage Name Wing 1 
Stage Manager  
Report Date 2010-02-17 15:52:45
Updated Date 2009-09-09 13:58:29
Description  
Commentary  
Status
Not Started 
startdate 00:00:00
enddate 00:00:00
originalenddate 00:00:00
timetolerance
timetoleranceused False
budget 0
currentspend 0
remainingspend 0
costtolerance 0
costtoleranceused False

Products

Products Completed During the Period  
Products to be Completed Next Period  

Risks and Issues

Actual and Potential Problems, and Risk Update  
Issue Status  
Budget and Schedule Impact of any Changes  

Stage Status

Product Descriptions Approved Yes
Work Packages Defined Yes
Stage Plan Produced Yes
Stage Started No
Stage Completed No
Stage Deliverables Approved No


User Activity [top]

Date Filter None

Admin
malc
cheryld
Emma
freddie
guy
juliet
matium
matt
neil
nick
paul
rose
sam
steve


Risk Log Summary [top]

Document: 'Risk Register' File: 'Risk Register.xls' Version: 1.1.a Date: 2009-09-24 10:08:27 (data provider:excelgembox)

Environmental Legal Contractual Resourcing Public Other Total
Closed Risks 1 0 1 0 1 1 4
Action Pending Risks 1 1 2 0 0 0 4
Open Risks 0 1 1 0 1 0 3
2 2 4 0 2 1 11

Risk Log Averages

Document: 'Risk Register' File: 'Risk Register.xls' Version: 1.1.a Date: 2009-09-24 10:08:27 (data provider:excelgembox)

All Risks Open and Pending Risks
Average Impact Medium Low
Average Probability 0.43 0.33
Average Proximity Long term Medium term
Average Risk Rating 3.15 3.76
Min Possible Risk Rating 0
Max Possible Risk Rating 100

Exposure to Risk

Document: 'Risk Register' File: 'Risk Register.xls' Version: 1.1.a Date: 2009-09-24 10:08:27 (data provider:excelgembox)

Expected Value of risks Inherent Cost Residual Cost
All RiskTotal 326000 276000
All Risk Probablised 113800 88600
Not Closed Total 186000 136000
Not Closed Probablised 65800 40600


Issue Log Summary [top]

Document: 'Issue Register' File: 'Issue Register.xls' Version: 1.0.a Date: 2009-09-07 17:18:36 (data provider:excelgembox)

RFC Off-Spec General Tot
Closed Issues 1 1 1 3
Action Pending Issues 0 1 1 2
Open Issues 1 3 2 6
2 5 4 11


Quality Log Summary [top]

Document: 'Quality Register' File: 'Quality Register.xls' Version: 0.0.f Date: 2010-02-17 08:43:41 (data provider:excelgembox)

Number Percentage
Number of Quality Activities Planned 6 -
Number of Quality Activities Undertaken 0 0
Number of Quality Activities passed 1st time 0 0
Number of Quality Activities completed as planned on time 0 0
Number of quality activities failed first time 0 0
Average number of Action Items 0 -
Number of retests passed 0 0
Of which were completed on time 0 0
Number of outstanding Quality Activities 6 1
Number of outstanding retests 0 0


Finance Log Summary [top]

Document: 'Project Plan' File: 'Project Finances.xls' Version: 0.0.b Date: 2009-09-08 10:32:42 (data provider:excelgembox)

Indicator Budget Completion (projected) Current
Health Rating Okay Okay Recovery
Income 4100000 4100000 1250000
Costs 4000049 4000049 51000
Contingency 99951 0
Margin 0 99951 1199000
% margin 0 0.0243782926829268 0.9592
Cash Position 199000
Level of Debtors 1000000


User-Specified Spreadsheet Tables [top]

riskthreshold

Document: 'Risk Register' File: 'Risk Register.xls' Version: 1.1.a Date: 2009-09-24 10:08:27 (data provider:excelgembox)

Risk ID Cause Event Effect Inherent risk rating Risk response Risk owner status residual risk rating exceeded report threshold
Town Hall Extension risk 2 Overun on Museum contract Possibility contractor may sart late End date slips on flagship project and increased cost of temp buildings 7.5 0 0 Action Pending 7.5 7.5
Town Hall Extension risk 7 some public inerest Lobby group may list trees at rear of site require us to apply for permits to cut down 5 0 0 Action Pending 5 5

keyissues

Document: 'Issue Register' File: 'Issue Register.xls' Version: 1.0.a Date: 2009-09-07 17:18:36 (data provider:excelgembox)

Issue Number Type Description Priority Status Date of last update Priority for Escalation
Town Hall extension Issue7 RFC New regulations require changes to lighting arrangements Low Open 2009-09-07 00:00:00 6
Town Hall extension Issue3 P Where will we hold the twinning ceremony High Open 2009-09-07 00:00:00 5

qualityactivitylist

Document: 'Quality Register' File: 'Quality Register.xls' Version: 0.0.f Date: 2010-02-17 08:43:41 (data provider:excelgembox)

Quality ID Product ID/Title Method of Quality Checking Responsibility Name/Role Planned Activity Date Actual Activity Date Result Number of action items Planned Completion Date Actual Completion Date
Town Hall Extension 3 inspection inspection tim 2010-06-01 00:00:00
Town Hall Extension 2 inspection inspection sue 2010-03-01 00:00:00
Town Hall Extension 1 inspection inspection malc 2010-01-01 00:00:00
Town Hall Extension 6 inspection inspection tim 2010-10-01 00:00:00
Town Hall Extension 5 inspection inspection sue 2010-09-01 00:00:00
Town Hall Extension 4 inspection inspection malc 2010-08-01 00:00:00


User-Specified MSP Plans [top]

Project Plan Support Tool.xls

Document: 'Project Plan' File: 'Project Plan Support Tool.xls' Version: 0.0.b Date: 2009-09-07 17:28:47 Interface: server, XLS file

Task ID Level Task Name Percent Complete Start Finish Resources
0 0 Town Hall Extension 0% 2009-09-01 2010-11-01 [malc 80%][sue 50%][tim 50%][joan 50%][megan 100%][joe 100%]
1 1 Planning permision 0% 2009-09-01 2009-10-01
2 1 prepare alternate offices and move 0% 2009-09-01 2009-11-01
3 1 Footings 0% 2009-10-01 2009-12-01
4 1 shell 0% 2009-11-01 2010-03-01
5 1 fitting 0% 2010-02-01 2010-08-01
6 1 services 0% 2010-02-01 2010-10-01
7 1 commissioning 0% 2010-09-01 2010-11-01
8 1 environmental sculpting 0% 2010-06-01 2010-11-01
9 1 Move in 0% 2010-08-01 2010-11-01