Summary Information [top]
| General |
| Project Name |
New Finances System |
| Report Date |
2010-02-17 15:52:18 |
| Updated Date |
2010-02-08 14:53:12 |
| Description |
Developing a new finances system for the Council.
This will cover the full range of council activities both income and expense. |
| Commentary |
Just started but looking good |
| Status |
 Started |
| Project_Manager |
Malcolm West |
| Project_Sponsor |
Guy Holford |
| Business_Area |
Execs office |
| Customer |
Terry Jones FD |
| Method_Template |
DSDM Atern |
| Value |
600000 |
| Duration |
67 |
| Risk |
9 |
| Reward |
8 |
| Strategic_Alignment |
good |
Project Roles [top]
| Business Sponsor |
juliet
|
| Business Visionary |
neil
|
| Project Manager |
malc
|
| Team Leader |
paul
|
Increment Highlight Report [top]
| General |
| Increment Name |
Iteration1 |
| Increment Manager |
|
| Report Date |
2010-02-17 15:52:18 |
| Updated Date |
2009-09-29 10:15:15 |
| Description |
rsourc and information gathering and developing an example data structure |
| Commentary |
Still some delay in getting data from Highways and Housing |
| Status |
 Started |
| Number_of_Timeboxes |
0 |
| Further_notes |
|
Products
| Products Completed During the Period |
|
| Products to be Completed Next Period |
|
Risks and Issues
| Actual and Potential Problems, and Risk Update |
|
| Issue Status |
|
| Budget and Schedule Impact of any Changes |
|
Increment Status
| Timebox 1 |
Yes |
| Timebox 2 |
Yes |
| Timebox 3 |
No |
| Deployment |
No |
|
|
No |
|
|
No |
Increment Highlight Report [top]
| General |
| Increment Name |
Iteration2 |
| Increment Manager |
|
| Report Date |
2010-02-17 15:52:18 |
| Updated Date |
|
| Description |
|
| Commentary |
|
| Status |
 |
Products
| Products Completed During the Period |
|
| Products to be Completed Next Period |
|
Risks and Issues
| Actual and Potential Problems, and Risk Update |
|
| Issue Status |
|
| Budget and Schedule Impact of any Changes |
|
Increment Status
| Timebox 1 |
No |
| Timebox 2 |
No |
| Timebox 3 |
No |
| Deployment |
No |
|
|
No |
|
|
No |
Increment Highlight Report [top]
| General |
| Increment Name |
Iteration3 |
| Increment Manager |
|
| Report Date |
2010-02-17 15:52:18 |
| Updated Date |
|
| Description |
|
| Commentary |
|
| Status |
 |
Products
| Products Completed During the Period |
|
| Products to be Completed Next Period |
|
Risks and Issues
| Actual and Potential Problems, and Risk Update |
|
| Issue Status |
|
| Budget and Schedule Impact of any Changes |
|
Increment Status
| Timebox 1 |
No |
| Timebox 2 |
No |
| Timebox 3 |
No |
| Deployment |
No |
|
|
No |
|
|
No |
Increment Highlight Report [top]
| General |
| Increment Name |
Iteration4 |
| Increment Manager |
|
| Report Date |
2010-02-17 15:52:18 |
| Updated Date |
|
| Description |
|
| Commentary |
|
| Status |
 |
Products
| Products Completed During the Period |
|
| Products to be Completed Next Period |
|
Risks and Issues
| Actual and Potential Problems, and Risk Update |
|
| Issue Status |
|
| Budget and Schedule Impact of any Changes |
|
Increment Status
| Timebox 1 |
No |
| Timebox 2 |
No |
| Timebox 3 |
No |
| Deployment |
No |
|
|
No |
|
|
No |
User Activity [top]

| Admin |
 |
| malc |
 |
| cheryld |
 |
| guy |
 |
| juliet |
 |
| lisa |
 |
| mary |
 |
| matium |
 |
| matt |
 |
| neil |
 |
| nick |
 |
| paul |
 |
| pete |
 |
Risk Log Summary [top]
Document: 'Delivery Control Pack' File: 'Risk Log.xls' Version: 1.0.a Date: 2009-09-29 10:46:39 (data provider:excelgembox)
|
|
regulatory |
technical |
operational |
employee related |
revenue |
other |
Total |
| Closed Risks |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
| Action Pending Risks |
0 |
1 |
0 |
1 |
0 |
0 |
2 |
| Open Risks |
2 |
0 |
1 |
0 |
0 |
0 |
3 |
|
|
2 |
1 |
1 |
1 |
0 |
0 |
5 |
Risk Log Averages
Document: 'Delivery Control Pack' File: 'Risk Log.xls' Version: 1.0.a Date: 2009-09-29 10:46:39 (data provider:excelgembox)
|
|
All Risks |
Open and Pending Risks |
| Average Impact |
Medium |
Medium |
| Average Probability |
0.29 |
0.29 |
| Average Proximity |
Medium term |
Medium term |
| Average Risk Rating |
2.86 |
2.86 |
|
|
|
|
| Min Possible Risk Rating |
0 |
|
| Max Possible Risk Rating |
100 |
|
Exposure to Risk
Document: 'Delivery Control Pack' File: 'Risk Log.xls' Version: 1.0.a Date: 2009-09-29 10:46:39 (data provider:excelgembox)
| Expected Value of risks |
Inherent Cost |
Residual Cost |
| All RiskTotal |
0 |
0 |
| All Risk Probablised |
0 |
0 |
| Not Closed Total |
0 |
0 |
| Not Closed Probablised |
0 |
0 |
Issue Log Summary [top]
Document: 'Delivery Control Pack' File: 'Issue Log.xls' Version: 0.0.b Date: 2009-09-29 10:49:11 (data provider:excelgembox)
|
|
RFC |
Off-Spec |
General |
Tot |
| Closed Issues |
0 |
0 |
0 |
0 |
| Action Pending Issues |
0 |
0 |
0 |
0 |
| Open Issues |
1 |
0 |
0 |
1 |
|
|
1 |
0 |
0 |
1 |
Quality Log Summary [top]
Document: 'Solution Assurance' File: 'Testing Log.xls' Version: 0.0.a Date: 2009-09-29 08:58:38 (data provider:excelgembox)
|
|
Number |
Percentage |
| Number of Quality Activities Planned |
0 |
- |
| Number of Quality Activities Undertaken |
0 |
0 |
| Number of Quality Activities passed 1st time |
0 |
0 |
| Number of Quality Activities completed as planned on time |
0 |
0 |
|
|
|
|
| Number of quality activities failed first time |
0 |
0 |
| Average number of Action Items |
0 |
- |
|
|
|
|
| Number of retests passed |
0 |
0 |
| Of which were completed on time |
0 |
0 |
|
|
|
|
|
|
|
|
|
|
|
|
| Number of outstanding Quality Activities |
0 |
0 |
| Number of outstanding retests |
0 |
0 |
Finance Log Summary [top]
Document: 'Delivery Plan' File: 'Project Finances.xls' Version: 0.0.b Date: 2009-09-29 10:38:03 (data provider:excelgembox)
| Indicator |
Budget |
Completion (projected) |
Current |
| Health Rating |
Okay |
Okay |
Good |
| Income |
600000 |
600000 |
400000 |
| Costs |
575000 |
575000 |
152000 |
| Contingency |
25000 |
|
0 |
| Margin |
0 |
25000 |
248000 |
| % margin |
0 |
0.0416666666666667 |
0.62 |
| Cash Position |
|
|
248000 |
| Level of Debtors |
|
|
0 |
User-Specified Spreadsheet Tables [top]
riskthreshold
Document: 'Delivery Control Pack' File: 'Risk Log.xls' Version: 1.0.a Date: 2009-09-29 10:46:39 (data provider:excelgembox)
| Risk ID |
Cause |
Event |
Effect |
Inherent risk rating |
Risk response |
Risk owner |
status |
residual risk rating |
exceeded report threshold |
| New Finances system risk 4 |
System may be more efficient and require less double keying of data |
Union concerned about staff reductions |
slow input to process |
9 |
0 |
0 |
Action Pending |
9 |
9 |
keyissues
Document: 'Delivery Control Pack' File: 'Issue Log.xls' Version: 0.0.b Date: 2009-09-29 10:49:11 (data provider:excelgembox)
| Issue Number |
Type |
Description |
Priority |
Status |
Date of last update |
Priority for Escalation |
| New finances project Issue1 |
RFC |
There is much more and more complex data from housing than had been anticipated or allowed for |
Urgent |
Open |
|
7 |
User-Specified MSP Plans [top]
project plan.mpp
File: 'project plan.mpp' Version: 0.0.a Date: 2009-09-29 10:20:39
| Task ID |
Level |
Task Name |
Percent Complete |
Start |
Finish |
Resources |
| 0 |
0 |
CRM Software Development |
95% |
2007-01-05 |
2007-12-27 |
|
| 1 |
1 |
Requirements Gathering |
100% |
2007-01-05 |
2007-07-05 |
[malc 15%] [guy 20%] [judy 30%] [neil 10%] |
| 2 |
1 |
Design and Prototyping |
100% |
2007-01-22 |
2007-03-19 |
[sam 30%] [malc 10%] [guy 20%] [neil 10%] |
| 3 |
1 |
Data framework |
100% |
2007-02-19 |
2007-05-24 |
[matt 50%] [guy 10%] [neil 25%] |
| 4 |
1 |
web reporting interface |
100% |
2007-03-05 |
2007-10-19 |
[matt 10%] [malc 10%] [guy 15%] [judy 70%] |
| 5 |
1 |
Integration and transfer interface |
94% |
2007-05-14 |
2007-12-03 |
[matt 30%] [sam 60%] [malc 10%] [guy 50%] |
| 6 |
1 |
User Interface |
94% |
2007-06-18 |
2007-11-20 |
[matt 50%] [sam 30%] [malc 10%] [guy 50%] [neil 5%] |
| 7 |
1 |
marketing Launch |
30% |
2007-11-21 |
2007-12-27 |
|