PROJECT in a box - Project Report - Portfolio: Local Authority projects, Report Date: 2010-02-17 15:51:34, Project: Pedestianisation

| Project | Stage |
|---|---|
| Pedestianisation | Stakeholder consultation |
On Track |
On Track |
| General | |
|---|---|
| Project Name | Pedestianisation |
| Report Date | 2010-02-17 15:52:07 |
| Updated Date | 2009-10-06 10:18:10 |
| Description | Removing traffic from the high street during shop opening hours. requiring some changes to surrounding roads, a move of the town centre bus stops and a range of communications activities |
| Commentary | Mostly being very well receved by shop owners and shoppers alike although there are a few issues to address |
| Status | On Track |
| Project_Manager | Sue Perkins |
| Project_Sponsor | Ali Bongo |
| Business_Area | Estates |
| Customer | Cllr Jones |
| Method_Template | P22009 core |
| Value | 1800000 |
| Duration | 28 |
| Risk | 7 |
| Reward | 9 |
| Strategic_Alignment | good |
| Executive | fred |
|---|---|
| Project Assurance | paul |
| Project Board | fred lisa mark |
| Project Manager | guy |
| Senior Supplier | lisa |
| Senior User | mark |
| Team Manager | malc neil |
PROJECT in a box - Project Report - Portfolio: Local Authority projects, Report Date: 2010-02-17 15:51:34, Project: Pedestianisation
| General | |
|---|---|
| Stage Name | Stakeholder consultation |
| Stage Manager | |
| Report Date | 2010-02-17 15:52:07 |
| Updated Date | 2009-09-08 11:12:38 |
| Description | |
| Commentary | |
| Status | On Track |
| Products Completed During the Period | |
|---|---|
| Products to be Completed Next Period |
| Actual and Potential Problems, and Risk Update | |
|---|---|
| Issue Status | |
| Budget and Schedule Impact of any Changes |
| Product Descriptions Approved | |
|---|---|
| Work Packages Defined | |
| Stage Plan Produced | |
| Stage Started | |
| Stage Completed | |
| Stage Deliverables Approved |
PROJECT in a box - Project Report - Portfolio: Local Authority projects, Report Date: 2010-02-17 15:51:34, Project: Pedestianisation
| Date Filter | None |
|---|

| Admin | ![]() |
| malc | ![]() |
| cheryld | ![]() |
| fred | ![]() |
| freddie | ![]() |
| guy | ![]() |
| lisa | ![]() |
| mark | ![]() |
| neil | ![]() |
| nick | ![]() |
| nicola | ![]() |
| paul | ![]() |
| rose | ![]() |
| steve | ![]() |
| tim | ![]() |
PROJECT in a box - Project Report - Portfolio: Local Authority projects, Report Date: 2010-02-17 15:51:34, Project: Pedestianisation
Document: 'Risk Register' File: 'Risk Register.xls' Version: 0.1.a Date: 2009-09-08 11:54:42 (data provider:excelgembox)
| technical | commercial | legal | community | environmental | other | Total | |
| Closed Risks | 0 | 1 | 1 | 1 | 0 | 0 | 3 |
| Action Pending Risks | 0 | 0 | 1 | 1 | 1 | 0 | 3 |
| Open Risks | 1 | 0 | 1 | 0 | 0 | 0 | 2 |
| 1 | 1 | 3 | 2 | 1 | 0 | 8 |
Document: 'Risk Register' File: 'Risk Register.xls' Version: 0.1.a Date: 2009-09-08 11:54:42 (data provider:excelgembox)
| All Risks | Open and Pending Risks | |
| Average Impact | Medium | Low |
| Average Probability | 0.25 | 0.32 |
| Average Proximity | Medium term | Medium term |
| Average Risk Rating | 3.09 | 3.24 |
| Min Possible Risk Rating | 0 | |
| Max Possible Risk Rating | 100 |
Document: 'Risk Register' File: 'Risk Register.xls' Version: 0.1.a Date: 2009-09-08 11:54:42 (data provider:excelgembox)
| Expected Value of risks | Inherent Cost | Residual Cost |
| All RiskTotal | 167000 | 87000 |
| All Risk Probablised | 73900 | 43700 |
| Not Closed Total | 132000 | 72000 |
| Not Closed Probablised | 67400 | 39200 |
PROJECT in a box - Project Report - Portfolio: Local Authority projects, Report Date: 2010-02-17 15:51:34, Project: Pedestianisation
Document: 'Issue Register' File: 'Issue Register.xls' Version: 0.0.b Date: 2009-09-08 11:59:10 (data provider:excelgembox)
| RFC | Off-Spec | General | Tot | |
| Closed Issues | 1 | 0 | 2 | 3 |
| Action Pending Issues | 2 | 0 | 0 | 2 |
| Open Issues | 0 | 1 | 0 | 1 |
| 3 | 1 | 2 | 6 |
PROJECT in a box - Project Report - Portfolio: Local Authority projects, Report Date: 2010-02-17 15:51:34, Project: Pedestianisation
Document: 'Quality Register' File: 'Quality Register.xls' Version: 0.0.c Date: 2009-09-25 14:04:28 (data provider:excelgembox)
| Number | Percentage | |
| Number of Quality Activities Planned | 3 | - |
| Number of Quality Activities Undertaken | 0 | 0 |
| Number of Quality Activities passed 1st time | 0 | 0 |
| Number of Quality Activities completed as planned on time | 0 | 0 |
| Number of quality activities failed first time | 0 | 0 |
| Average number of Action Items | 0 | - |
| Number of retests passed | 0 | 0 |
| Of which were completed on time | 0 | 0 |
| Number of outstanding Quality Activities | 3 | 1 |
| Number of outstanding retests | 0 | 0 |
PROJECT in a box - Project Report - Portfolio: Local Authority projects, Report Date: 2010-02-17 15:51:34, Project: Pedestianisation
Document: 'Project Plan' File: 'Project Finances.xls' Version: 0.0.b Date: 2009-09-08 12:08:41 (data provider:excelgembox)
| Indicator | Budget | Completion (projected) | Current |
| Health Rating | Okay | Recovery | Good |
| Income | 850000 | 850000 | 700000 |
| Costs | 840000 | 853000 | 608000 |
| Contingency | 10000 | 0 | |
| Margin | 0 | -3000 | 92000 |
| % margin | 0 | -0.00352941176470588 | 0.131428571428571 |
| Cash Position | 92000 | ||
| Level of Debtors | 0 |
PROJECT in a box - Project Report - Portfolio: Local Authority projects, Report Date: 2010-02-17 15:51:34, Project: Pedestianisation
Document: 'Issue Register' File: 'Issue Register.xls' Version: 0.0.b Date: 2009-09-08 11:59:10 (data provider:excelgembox)
| Issue Number | Type | Description | Priority | Status | Date of last update | Priority for Escalation |
|---|
Document: 'Quality Register' File: 'Quality Register.xls' Version: 0.0.c Date: 2009-09-25 14:04:28 (data provider:excelgembox)
| Quality ID | Product ID/Title | Method of Quality Checking | Responsibility Name/Role | Planned Activity Date | Actual Activity Date | Result | Number of action items | Planned Completion Date | Actual Completion Date |
|---|---|---|---|---|---|---|---|---|---|
| Pedestrianisation 1 | testing | inspection | Mark | 2009-11-01 00:00:00 | |||||
| Pedestrianisation 2 | testing | consumer survey | Mark | 2009-11-02 00:00:00 | |||||
| Pedestrianisation 3 | testing | retailer survey | Mark | 2009-11-03 00:00:00 |
Document: 'Risk Register' File: 'Risk Register.xls' Version: 0.1.a Date: 2009-09-08 11:54:42 (data provider:excelgembox)
| Risk ID | Cause | Event | Effect | Inherent risk rating | Risk response | Risk owner | status | residual risk rating | exceeded report threshold |
|---|---|---|---|---|---|---|---|---|---|
| Pedestrianisation risk 3 | cannot offer their buy and fit service | Car part shop threatening to challange plans | delay or compensation possible | 15 | Consider an alternate access route to the rear of the store | 0 | Open | 12 | 12 |
PROJECT in a box - Project Report - Portfolio: Local Authority projects, Report Date: 2010-02-17 15:51:34, Project: Pedestianisation
Document: 'Project Plan' File: 'Project Plan Support Tool.xls' Version: 0.0.b Date: 2009-09-08 14:31:16 Interface: server, XLS file
| Task ID | Level | Task Name | Percent Complete | Start | Finish | Resources |
| 0 | 0 | Pedestrianisation | 0% | 2009-06-01 | 2010-02-01 |