Summary Information [top]

General
Project Name New Road playground 
Report Date 2010-02-17 15:51:40
Updated Date 2009-10-06 10:14:21
Description Playground redevelopment at new road, providing a resource for the local community in conjuction with several funding bodies. 
Commentary All going well, a trip with the primary school to see the manufacturing site was a particular highlight. 
Status
On Track 
Project_Manager Malcolm West
Project_Sponsor John Noakes
Business_Area estates
Customer Cllr Smith
Method_Template P22009 core
Value 28000
Duration 10
Risk 2
Reward 7
Strategic_Alignment excellent

Project Roles [top]

Executive fred
Project Assurance paul
Project Board fred
Project Manager guy
PSO neil
Team Manager malc

Stage Highlight Report [top]

General
Stage Name Tender exercise 
Stage Manager  
Report Date 2010-02-17 15:51:40
Updated Date 2009-09-08 16:37:31
Description  
Commentary  
Status
Completed 

Products

Products Completed During the Period  
Products to be Completed Next Period  

Risks and Issues

Actual and Potential Problems, and Risk Update  
Issue Status  
Budget and Schedule Impact of any Changes  

Stage Status

Product Descriptions Approved Yes
Work Packages Defined Yes
Stage Plan Produced Yes
Stage Started Yes
Stage Completed Yes
Stage Deliverables Approved Yes


Stage Highlight Report [top]

General
Stage Name Phase 1 
Stage Manager  
Report Date 2010-02-17 15:51:40
Updated Date 2009-09-09 14:15:56
Description  
Commentary  
Status
Completed 
startdate 00:00:00
enddate 00:00:00
originalenddate 00:00:00
timetolerance
timetoleranceused False
budget 0
currentspend 0
remainingspend 0
costtolerance 0
costtoleranceused False

Products

Products Completed During the Period  
Products to be Completed Next Period  

Risks and Issues

Actual and Potential Problems, and Risk Update  
Issue Status  
Budget and Schedule Impact of any Changes  

Stage Status

Product Descriptions Approved Yes
Work Packages Defined Yes
Stage Plan Produced Yes
Stage Started Yes
Stage Completed Yes
Stage Deliverables Approved Yes


Stage Highlight Report [top]

General
Stage Name Phase 2 
Stage Manager  
Report Date 2010-02-17 15:51:40
Updated Date 2009-09-09 14:16:06
Description  
Commentary  
Status
Started 
startdate 00:00:00
enddate 00:00:00
originalenddate 00:00:00
timetolerance
timetoleranceused False
budget 0
currentspend 0
remainingspend 0
costtolerance 0
costtoleranceused False

Products

Products Completed During the Period  
Products to be Completed Next Period  

Risks and Issues

Actual and Potential Problems, and Risk Update  
Issue Status  
Budget and Schedule Impact of any Changes  

Stage Status

Product Descriptions Approved Yes
Work Packages Defined Yes
Stage Plan Produced Yes
Stage Started Yes
Stage Completed No
Stage Deliverables Approved No


User Activity [top]

Date Filter None

Admin
malc
cheryld
fred
freddie
guy
neil
nick
paul


Risk Log Summary [top]

Document: 'Risk Register' File: 'Risk Register.xls' Version: 0.0.b Date: 2009-09-08 16:16:40 (data provider:excelgembox)

Environmental Legal Contractual Resourcing Public Other Total
Closed Risks 1 2 1 0 2 1 7
Action Pending Risks 2 0 0 0 0 0 2
Open Risks 0 0 0 0 1 0 1
3 2 1 0 3 1 10

Risk Log Averages

Document: 'Risk Register' File: 'Risk Register.xls' Version: 0.0.b Date: 2009-09-08 16:16:40 (data provider:excelgembox)

All Risks Open and Pending Risks
Average Impact Medium Low
Average Probability 0.46 0.37
Average Proximity Long term Long term
Average Risk Rating 3.02 4.17
Min Possible Risk Rating 0
Max Possible Risk Rating 100

Exposure to Risk

Document: 'Risk Register' File: 'Risk Register.xls' Version: 0.0.b Date: 2009-09-08 16:16:40 (data provider:excelgembox)

Expected Value of risks Inherent Cost Residual Cost
All RiskTotal 15200 65200
All Risk Probablised 6360 31060
Not Closed Total 13000 13000
Not Closed Probablised 5600 5600


Issue Log Summary [top]

Document: 'Issue Register' File: 'Issue Register.xls' Version: 0.0.b Date: 2009-09-08 16:36:50 (data provider:excelgembox)

RFC Off-Spec General Tot
Closed Issues 1 1 1 3
Action Pending Issues 1 1 0 2
Open Issues 0 0 0 0
2 2 1 5


Quality Log Summary [top]

Document: 'Quality Register' File: 'Quality Register.xls' Version: 1.0.a Date: 2009-09-25 14:05:40 (data provider:excelgembox)

Number Percentage
Number of Quality Activities Planned 2 -
Number of Quality Activities Undertaken 1 0.5
Number of Quality Activities passed 1st time 1 1
Number of Quality Activities completed as planned on time 1 1
Number of quality activities failed first time 0 0
Average number of Action Items 0 -
Number of retests passed 0 0
Of which were completed on time 0 0
Number of outstanding Quality Activities 1 0.5
Number of outstanding retests 0 0


Finance Log Summary [top]

Document: 'Project Plan' File: 'Project Finances.xls' Version: 0.0.b Date: 2009-09-08 16:28:40 (data provider:excelgembox)

Indicator Budget Completion (projected) Current
Health Rating Okay Okay Okay
Income 27500 27500 14000
Costs 25518 26932 10992
Contingency 1982 0
Margin 0 568 3008
% margin 0 0.0206545454545455 0.214857142857143
Cash Position 1508
Level of Debtors 1500


User-Specified Spreadsheet Tables [top]

keyissues

Document: 'Issue Register' File: 'Issue Register.xls' Version: 0.0.b Date: 2009-09-08 16:36:50 (data provider:excelgembox)

Issue Number Type Description Priority Status Date of last update Priority for Escalation
New Road Playground Issue3 RFC opening to now be a civit affair with major attending High Action Pending 2009-09-07 00:00:00 5

qualityactivitylist

Document: 'Quality Register' File: 'Quality Register.xls' Version: 1.0.a Date: 2009-09-25 14:05:40 (data provider:excelgembox)

Quality ID Product ID/Title Method of Quality Checking Responsibility Name/Role Planned Activity Date Actual Activity Date Result Number of action items Planned Completion Date Actual Completion Date
New Road Playground 2 inspection survey sue 2009-09-01 00:00:00 2009-09-01 00:00:00 Pass 2009-09-01 00:00:00 2009-09-01 00:00:00
New Road Playground 1 inspection inspection malc 2010-01-01 00:00:00

riskthreshold

Document: 'Risk Register' File: 'Risk Register.xls' Version: 0.0.b Date: 2009-09-08 16:16:40 (data provider:excelgembox)

Risk ID Cause Event Effect Inherent risk rating Risk response Risk owner status residual risk rating exceeded report threshold
New Road Playground risk 5 0 possible missuse by teenagers more substantial equipment and extension to park warden duties 7.5 0 0 Open 7.5 7.5

healthcheckoverview

Document: 'Health Check' File: 'Health Check.xls' Version: 0.0.b Date: 2009-09-08 16:52:20 (data provider:excelgembox)

Project Checklist % Completed % Acceptable Rating
New Road Playground 2.4 - Giving ad hoc direction 100 60 60
New Road Playground 3 - Initiating a Project 93 73 68
New Road Playground 2.3 - Authorise a Stage or Exception Plan 100 70 70
New Road Playground 2 - Directing a Project 100 78 78
New Road Playground 2.5 - Authorising project closure 100 80 80
New Road Playground 2.2 - Authorise the project 100 85 85
New Road Playground 2.1 - Authorise initiation 100 91 91
New Road Playground 1 - Starting up a project 100 100 100


User-Specified MSP Plans [top]

Project Plan Support Tool.xls

Document: 'Project Plan' File: 'Project Plan Support Tool.xls' Version: 0.0.b Date: 2009-09-08 16:33:52 Interface: server, XLS file

Task ID Level Task Name Percent Complete Start Finish Resources
0 0 New Road Playground 0% 2009-07-01 2009-10-01 [malc 80%][sue 50%][tim 50%][joan 50%][megan 100%][joe 100%]
1 1 clear site 0% 2009-07-01 2009-07-15
2 1 footings 0% 2009-07-12 2009-07-30
3 1 assemble 0% 2009-08-01 2009-09-20
4 1 commissioning 0% 2009-09-21 2009-09-28
5 1 test and handover 0% 2009-09-30 2009-10-01